黑料网

3/3- ISB Construction Updates

Work in Progress:

  • Augarcast pile installation is complete.
  • Grade beams and pile caps are ongoing.  Currently complete along column line 1 on the North and working south.
  • Started forming basement retaining wall along column line 1.
  • Forming of Elevator #1 (North) hoistway walls has begun.

Looking ahead:

  • Continue grade beam and pile cap installation working south.
  • Pour basement retaining wall scheduled for 3/4/2016.
  • Pour first lift of north elevator hoistway schedule for 3/8/2016.
POSTED: Thursday, March 3, 2016 03:25 PM
Updated: Thursday, January 19, 2017 09:05 AM