黑料网

1/28- Smith Hall Renovation Updates

Work in progress:

  • Electric rough-in is in progress in rooms 101 and 104. Floor box rough-in is complete.
  • Completing the under-slab plumbing tie-ins in 101 and 104.
  • Electrical raceways are being installed the crawl space.
  • New first floor restroom under-slab sanitary piping is approximately 75% complete.
  • Demolition of the receiving area and machine shop partitions are approximately 75% complete.
  • Temporary wall and door installation will be completed 1/28/16.
  • Second floor abatement in 223, restroom, 216 & 217 is 95% complete.
  • Tile and abatement in 205 is in progress.

Looking a week ahead:

  • Complete 2nd floor demolition and remaining misc. items.
  • Core drill 1/29/16 for sanitary service extending to exterior through exterior walls.
  • Underground exterior sanitary work will begin 2/1/16
  • Tie into storm line for new addition down spout.
  • Addition slab on grade prep and pour pending underground progress and weather.
  • Remaining 1st floor demolition items.
  • General trades contractor will mobilize and begin layout for wall partitions in 101, 104, 223 and machine shop.
POSTED: Thursday, January 28, 2016 01:08 PM
Updated: Thursday, January 19, 2017 09:05 AM