2/25- Smith Hall Renovation Updates

Work in Progress:

  • Wall layout and coordination has begun in rooms 101 & 104, 223 and machine shop.
  • Plumbing trenches in 101 & 104 have been backfilled and prepared for floor slab pour.
  • Underground plumbing rough-in was inspected and approved on 2/24/16.

Looking ahead:

  • Pour floor slab in fills in 101 & 104 on 2/26/16.
  • Pour floor slab in new first floor restroom on 2/26/16.
  • Start framing 101, 104, 223 and machine shop.
  • Plumbing rough-in in new first floor restroom will begin.
  • Electrical rough-in following metal stud framing on first and second floors.
  • Facing brick masonry will continue at the addition weather permitting.