3/3- Smith Hall Renovation Update

Work in Progress:

  • Rooms 101-104: Wall framing and electric rough-in in progress.
  • Machine shop framing.
  • New restroom: Interior Wall framing, Electric rough-in, plumbing fixture carrier assembly rough-in.
  • Framing in 223 has begun along with electrical rough-in.
  • Demolition has begun in 3rd floor restrooms.

Looking ahead:

  • S.A. Comunale mobilization (HVAC contractor)
  • Coordination drawings to be completed
  • Continue Framing rooms 101-104, 2 nd floor and machine shop.
  • Vent/beam fill in where existing uni vents were located. (1 st and 2nd floors). Starting 3/3.
  • Wall patching and drywall lamination throughout.
  • Perimeter wall installation.
  • Plumbing carriers in new rest room, above ground sanitary and water in restrooms.
  • Electrical rough in throughout 1 st and 2nd floor.
  • Face brick and remaining CMU pending weather. Exterior concrete will be in place.
  • Restroom demo and abatement. Abatement and demo to start Monday, 3/7 after Liebert unit is removed for storage.
POSTED: Thursday, March 3, 2016 03:26 PM
Updated: Thursday, January 19, 2017 09:05 AM