4/14- ISB Construction Updates

Work in Progress:

  • Start forming elevator #2 (south).
  • Grade beam and pile caps along column line #17 between A and G is in progress.
  • Pile caps for elevator #2 are complete.
  • Installing pile caps for Stair #3.

Looking forward:

  • Steel erection sequence #1 will begin on Monday, April 18th.
  • Start forming stair #3 and be ready for first pour on April 22nd.
  • Continue with retaining wall to column line B-17.
POSTED: Thursday, April 14, 2016 06:22 PM
Updated: Thursday, January 19, 2017 09:05 AM