黑料网

4/7- Smith Hall Renovation Updates

Work in Progress:

  • Pulling wire throughout for branch circuits.
  • Installing duct on 1st floor.
  • Complete domestic water rough-in on the 2nd floor.
  • Sanitary piping rough-in has been completed on the 3rd floor.
  • Completing remaining framing throughout.
  • Starting door frame installation.
  • Drywall delivery scheduled for 4/8/2016.
  • Steel delivery was 4/6/2016 and columns have been erected.

Looking forward:

  • Continue with steel erection.
  • HVAC unit curb delivery will follow steel erection.
  • Continue with HVAC duct on first floor.
  • Drywall hanging and taping to begin.
  • Door frame installation throughout.
  • Continue with electrical wire pulling.
POSTED: Thursday, April 7, 2016 12:00 AM
Updated: Saturday, December 3, 2022 01:02 AM