Year of Science
ºÚÁÏÍø College of Arts and Sciences is celebrating a Year of Science!
Work in Progress:
Chilled water service in the 3rd floor east mechanical room is 95% complete by EOB on 3/18. Will be ready for cooling system startup on 4/15.
Currently insulating the chilled water pipes in the 3rd floor wast mechanical room.
Steam reducing station…
3/17- Cunningham Hall Renovation Updates
Work in Progress: Chilled water service in the 3rd floor east mechanical room is 95% complete by EOB on 3/18. Will be ready for cooling system startup on 4/15. Currently insulating the chilled water pipes in the 3rd floor wast mechanical room. Steam reducing station…Work in Progress:
New restroom plumbing rough-in nearly complete.
Sheet metal duct rough-in has begun on the first floor and the new restroom areas.
Electrical floor boxes are 75% complete in 223.
Sanitary drain and toilet carriers are complete in the second floor.
3rd…
3/17- Smith Hall Renovation Updates
Work in Progress: New restroom plumbing rough-in nearly complete. Sheet metal duct rough-in has begun on the first floor and the new restroom areas. Electrical floor boxes are 75% complete in 223. Sanitary drain and toilet carriers are complete in the second floor. 3rd…Image
ºÚÁÏÍø Day at the Cleveland Film Festival (CIFF) is slated for April 6 at Tower City Cinemas in downtown Cleveland. Kent State is a sponsor of the festival and members of the Kent State community will receive $2 off any ticket to a film showing on that day. Kent…
April 6 is Kent State Day at the Cleveland International Film Festival
ºÚÁÏÍø Day at the Cleveland Film Festival (CIFF) is slated for April 6 at Tower City Cinemas in downtown Cleveland. Kent State is a sponsor of the festival and members of the Kent State community will receive $2 off any ticket to a film showing on that day. Kent…The Wick Poetry Center at ºÚÁÏÍø will expand its successful Traveling Stanzas project with $125,000 in new funding from the John S. and James L. Knight Foundation, as part of its Knight Arts Challenge.
The Knight Arts Challenge funds ideas that…
Kent State's Wick Poetry Center to Expand Traveling Stanzas Project With $125,000 in New Funding From Knight Foundation
The Wick Poetry Center at ºÚÁÏÍø will expand its successful Traveling Stanzas project with $125,000 in new funding from the John S. and James L. Knight Foundation, as part of its Knight Arts Challenge. The Knight Arts Challenge funds ideas that…Work in Progress:
Work continues on the chilled water service lines in the 3rd floor east mechanical room.
Work continues on the steam service in the 3rd floor west mechanical room.
Installation of AHU#1 in the 3rd floor east mechanical room continues.
Unit #4 duct tie in…
3/11- Cunningham Hall Renovation Update
Work in Progress: Work continues on the chilled water service lines in the 3rd floor east mechanical room. Work continues on the steam service in the 3rd floor west mechanical room. Installation of AHU#1 in the 3rd floor east mechanical room continues. Unit #4 duct tie in…Work in Progress:
Continuing the wall framing and electrical rough-in in room 101, 104, & 223.
Wall framing, electrical & plumbing rough-in continue in the new first floor restrooms.
Electrical floor box layout and core drilling has begun in 223.
Continuing the…
3/11- Smith Hall Renovation Update
Work in Progress: Continuing the wall framing and electrical rough-in in room 101, 104, & 223. Wall framing, electrical & plumbing rough-in continue in the new first floor restrooms. Electrical floor box layout and core drilling has begun in 223. Continuing the…Work in Progress:
Rooms 101-104: Wall framing and electric rough-in in progress.
Machine shop framing.
New restroom: Interior Wall framing, Electric rough-in, plumbing fixture carrier assembly rough-in.
Framing in 223 has begun along with electrical rough-in.
Demolition…
3/3- Smith Hall Renovation Update
Work in Progress: Rooms 101-104: Wall framing and electric rough-in in progress. Machine shop framing. New restroom: Interior Wall framing, Electric rough-in, plumbing fixture carrier assembly rough-in. Framing in 223 has begun along with electrical rough-in. Demolition…Work in Progress:
Augarcast pile installation is complete.
Grade beams and pile caps are ongoing. Currently complete along column line 1 on the North and working south.
Started forming basement retaining wall along column line 1.
Forming of Elevator #1 (North)…
3/3- ISB Construction Updates
Work in Progress: Augarcast pile installation is complete. Grade beams and pile caps are ongoing. Currently complete along column line 1 on the North and working south. Started forming basement retaining wall along column line 1. Forming of Elevator #1 (North)…Work in Progress:
Wall layout and coordination has begun in rooms 101 & 104, 223 and machine shop.
Plumbing trenches in 101 & 104 have been backfilled and prepared for floor slab pour.
Underground plumbing rough-in was inspected and approved on 2/24/16.
Looking…
2/25- Smith Hall Renovation Updates
Work in Progress: Wall layout and coordination has begun in rooms 101 & 104, 223 and machine shop. Plumbing trenches in 101 & 104 have been backfilled and prepared for floor slab pour. Underground plumbing rough-in was inspected and approved on 2/24/16. Looking…Work in Progress:
Phoenix air valve replacement in the Annex research labs continues per schedule.
Continuing the chilled water piping in the 3rd floor east mechanical room.
Continuing the demolition of AHU#3.
Looking forward:
Complete the demolition of AHU#3 in the…